Topology

In the "Topology" frame, the coordinates of section points and table with required field tests are shown.

We assign all field tests we want to display in our cross-section.

The field tests are usually projected perpendicularly to the geological section, but it is possible to shift them as well. The chainage of the field test and its distance from the geological section are displayed in the "Assigned field tests" table.

Next, the vertical shift of the field test must be defined.

  • None - standard option, the field test is displayed in the real altitude
  • On the terrain - the first point of the filed test is placed on the terrain
  • Input - user-defined vertical shift of the field test in the geological section

"Topology" Tab